written by MILSS7PSUK on 28/02/2022
Slight delay on work due to high winds that would have made the work impossible. Quickly rescheduled and completed within 3 days of original date. Scaffolders although early were great and help to clear my drive. Final Installation took a little longer than predicted as the roof was new and the tiles very difficult to move. Once completed all was explained and ALL rubbish cleared away. Best part is running our Dryer and only importing 10m! Thanks Project Solar UK very professional job.